Swimming pool construction stages: the order of 12 steps from site survey to stage payment

Swimming pool construction stages: the order of 12 steps from site survey to stage payment

Pool construction starts with a site survey and a ground investigation; each of the 12 steps through design, excavation, shell, pipework, waterproofing, finish and handover closes with a checkpoint.

AS

Project Manager · Mechatronics Engineer · Çilek Havuz

Published
Updated
Reading
11 min read

Listen to this article

Reading speed

This article can also be read and heard in:

Share

Pool construction starts with a site survey and a ground investigation; each of the 12 steps through design, excavation, shell, pipework, waterproofing, finish and handover closes with a checkpoint.

Short answer

The stages of pool construction are the technical sequence a reinforced concrete pool project follows from site survey to handover.

The order is not arbitrary: each step produces the input for the next, and each step ends with a measurable output and a stage payment point tied to it. No structural design is drawn without a ground investigation, no finish starts before the water-tightness test is passed, and no handover certificate is signed without a commissioning report. When pool construction follows this chain without skipping links, time and cost stay predictable.

This article does not repeat the general guide for people having a pool built or the article on cost. Its subject is the order in which work is done on site, what is checked at each step, which document is produced and which evidence each stage payment depends on. With a prefabricated pool some of the stages fall away; the sequence described here is for a reinforced concrete pool.

Short answer

The table below gives the typical sequence of a villa pool project, the checkpoint of each step and the document it produces.

Hotel and residential complex pools keep the same order; only the durations and the number of documents increase. The durations are the average ranges of the projects we have commissioned since 1993; ground, climate and the permit process change these ranges on every project.

Reinforced concrete pool construction stages

StepWorkCheckpointOutput / documentTypical duration
1Site survey and briefPlot, levels, access, water and power connection point, intended useSurvey report, dimension sketch1 day
2Ground investigationBoreholes, summer and winter water table level, soil class, bearing capacityGeotechnical report1-2 weeks
3Preliminary design and quotationPool type (skimmer or overflow), size, depth, equipment classPreliminary design, bill of quantities, quotation1-2 weeks
4Construction drawings and structural designShell thickness, reinforcement, uplift, seismic joint, pipework diagramStructural and mechanical construction drawings2-4 weeks
5Permit and approvalZoning status, municipal application; permit where the project requires onePermit or approval letter2-8 weeks depending on the municipality
6Setting out and excavationCorner levels, slope safety, groundwater observation, perimeter drainage bedExcavation level record2-5 days
7Drainage, blinding and below-slab pipeworkPerforated pipe and sump, gravel bed, blinding concrete, main drainDrainage photographs, pipe test3-5 days
8Reinforcement, formwork and shell concreteDouble layer of reinforcement, concrete cover, waterstop, pipe penetrations; C30/37, w/c ≤ 0.45Concrete delivery note, test samples, pour record1-2 weeks + 7 days curing
9Pipework and plant roomSuction and return lines, pressure test, pump and filter installation, electrical panelPressure test record1-2 weeks
10Waterproofing and water-tightness testCement-based flexible waterproofing, corner tape; 48-hour level monitoringWater-tightness test record1-2 weeks
11Finish, coping stone and surround pavingCeramic or glass mosaic, epoxy grout, coping stone, paving sloped away from the poolFinish checklist2-4 weeks
12Commissioning and handoverFirst fill, water balance, automation settings, operator trainingCommissioning report, handover certificate, warranty documents3-5 days
Durations are average ranges for a villa pool; step 5 varies with the municipality and the project, and the curing time in step 8 is the minimum period to wait after the concrete pour.

The rows of the table most often skipped are 2, 7 and 10. When the ground investigation is skipped, shell thickness and drainage are set by guesswork; when drainage is skipped, groundwater lifts the empty shell; when the water-tightness test is skipped, a leak ends up under the finish and the finish has to be removed to find it. None of the three is an expensive step; what is expensive is the repair after they are skipped.

Short answer

The site survey establishes the plot levels, access for the excavator and concrete mixer, the water and power connection point and the intended use of the pool.

The intended use decides the pool type: a skimmer pool needs less balance tank capacity and pipework, while an overflow pool is preferred in hotels and design-led villa projects for its surface cleaning and appearance. Because this choice sets the shell geometry, the balance tank and the size of the plant room, it is settled before the design.

The ground investigation answers two questions: the summer and winter level of the water table, and the bearing capacity of the soil. Under Archimedes' principle, when the water table rises above the pool floor, the empty shell is pushed upwards with a force equal to the weight of water it displaces; for an 8 x 4 m pool, a 1 m difference in water table means a force in the order of 32 tonnes. This figure puts the shell toe, the hydrostatic valve and the perimeter drainage into the design at step 4. The construction drawings also include the seismic joint between pool and building, the pipe penetrations and the reinforcement plan; for projects that need a permit, this file is submitted to the municipality. We prepare the municipal process and all the structural, electrical and architectural drawings required for the pool permit.

Short answer

Excavation starts with setting out: the four corners of the pool and the floor level are marked on the plot, and the excavation is opened wider than the outer face of the shell by a working allowance.

Groundwater is observed and photographed during excavation; a dry excavation does not mean dry ground. At the bottom of the excavation, perforated pipe and a gravel bed for perimeter drainage are laid so that they connect to the sump; blinding concrete is poured over them and the main drain line is taken through the blinding.

The shell concrete is the longest technical step on its own. A double layer of reinforcement is tied, cover spacers are fixed, a waterstop is placed in the floor-to-wall joint, and the skimmer, inlet nozzle and main drain sleeves are fixed to the reinforcement. The concrete arrives as class C30/37 with a water/cement ratio below 0.45; no water is added to the mixer on site, and samples are taken at every pour. Sprayed concrete or cast-in-formwork is chosen according to the design, and in both cases the shell is cured by keeping it wet for at least seven days. The structural work closes with the concrete sample results and the pour record; this stage payment depends on the concrete being poured and the samples being taken.

Structural work handover checklist

  • Excavation level and shell dimensions match the design; corner levels are recorded.
  • Perimeter drainage and sump are working, and the gravel bed has been photographed.
  • Class and admixture are written on the concrete delivery note, samples taken, pour record signed.
  • Waterstop and pipe penetration sleeves photographed before the pour.
  • Curing plan applied; formwork tie holes on the shell surface sealed.

Short answer

Pipework is laid while the shell is curing: suction from the skimmer or overflow channel, return to the inlet nozzles, main drain and balance tank lines are all brought together in the plant room.

Each line is capped and pressure tested, and the test record becomes an annex to the stage payment; a leak in a buried line cannot be found later without lifting the paving. The pump, filter, heat pump and dosing equipment are installed in the plant room at this step; the chemical store is planned as a separate, ventilated space away from the pump room.

Waterproofing is applied over the shell as a cement-based flexible layer, with tape at the corners and pipe penetrations. The pool is then filled and the water-tightness test is carried out: the level is monitored for 48 hours, the evaporation allowance is deducted, and the remaining loss is a leak. No finish starts before the test is passed; the rule exists because of the cost of repairing a leak that shows up after the finish is laid.

Short answer

The finish starts after the water-tightness test record.

Ceramic or glass mosaic is laid with pool-grade adhesive and the joints are filled with epoxy grout; the coping stone and surround paving slope away from the pool and are connected to a rain gutter and the garden drainage. The finish checklist covers joint gaps, waterproofing under the coping stone and paving falls. This step looks the longest in duration; material supply and grout curing set the programme.

Commissioning starts with the first fill: the water is balanced (alkalinity, pH and calcium hardness, in that order), the first filter backwash is done, automation and dosing are set and the heat pump is brought into service. Operator training is given to the owner or the technical staff; the test logbook, winterising instructions and chemical storage rules are part of this training. The handover certificate is signed together with the commissioning report, as-built drawings, equipment warranty documents and the operating manual; the final stage payment depends on this file.

Glossary

Setting out
Marking the pool corners and levels from the design on the plot; excavation is opened according to these marks.
Blinding concrete
Unreinforced levelling concrete poured on the floor of the excavation; it allows the shell reinforcement to be tied on a clean, level base.
Stage payment
An interim payment made against a completed work item; each stage payment is tied to an inspection record.
Pressure test
Capping the pipelines before they are buried and monitoring their tightness under pressure; documented with a record.
Water-tightness test
Filling the pool after waterproofing and before the finish, and monitoring level loss for 48 hours; the evaporation allowance is deducted.
As-built
The final drawings made of the work as it was actually built; buried pipe routes and equipment locations are read from these drawings.
Commissioning
The final technical step covering first fill, water balance, filter and automation settings and operator training; it closes with a report.

Short answer

The logic of the sequence derives from two engineering rules.

The first is that each step produces the input for the next: the ground investigation sets the shell, the shell sets the pipework, the pipework sets the waterproofing, and the waterproofing sets the finish. The second is to put a cheap test in front of every job that is expensive to undo: a pressure test before burying, a water-tightness test before the finish, a commissioning report before handover. Tying stage payments to these records keeps the sequence intact on site as well; payment moves with evidence.

This discipline has been carried over to pool construction from the site practice of water tanks and treatment structures. A reinforced concrete pool shell is a structure, and it proceeds like one: ground first, then design, then structural work, then finishing. The programme of a pool project is read from this sequence too; the way to shorten it is not to skip steps but to finish steps 2 to 5 before the excavation season.

Next step

Let us discuss your project in the way that suits you best.

You can fill in the form for a written quote, schedule a video project presentation or ask us to survey your project site.

  • Get a Quote

    Send us your dimensions and expectations in writing.

  • Online presentation

    Video project presentation

  • On-site survey

    Inspection at your project site

// 01 · Products in this article

For the work described in this article, pool mechanical equipment.

Each card leads to the product page with its data sheet, model list and quotation.

List prices as of 9 October 2026, excl. VAT.

Product groups

// 02 · Product groups

Compare the products on this topic on their category pages.

Each card leads to a product category; models, technical sheets and list prices are there.

  • Pool Mechanical Equipment

    Product category

    Pool Mechanical Equipment

    Circulation pumps, filters, valves and automation: the mechanical infrastructure that forms the heart of the pool.

    65 products
  • Pool Lining Systems

    Product category

    Pool Lining Systems

    PVC liner, membrane, ceramic tile and glass mosaic: lining materials that make the pool watertight and form its finished surface.

    20 products
  • Pool Disinfection Systems

    Product category

    Pool Disinfection Systems

    Fully automatic pool water disinfection that reduces chemical use with salt electrolysis, UV disinfection and smart dosing systems.

    52 products

// 03 · Related service

The work in this article, we deliver from design to handover.

Swimming Pool Construction

Çilek Havuz service

Swimming Pool Construction

Reinforced-concrete, prefabricated and infinity swimming pools, built turnkey for villa, residential and commercial projects.

Swimming pool construction is a turnkey build in which the site survey, structural and mechanical design, excavation, reinforced-concrete shell, waterproofing, finish, filtration plumbing and commissioning run under a single contract. The written project schedule follows the site survey.

How we work

  1. 01Initial meeting and site surveyWe inspect the site and listen to the brief.
  2. 02Design and quotationWe give the cost item by item, in writing.
  3. 03ExecutionThe same team builds to a written schedule.
  4. 04Handover and commissioningWe start the systems and explain their use.
  5. 05Maintenance and technical supportWe provide periodic maintenance and support.

// 04 · Guides

On Pool Construction, more articles to read.

First the articles directly related to this one, then the newest articles on the topic.

All pool construction articles

// 05 · Company & Contact

To talk about your project, call or write to us.

Legal Name

Çilek Havuz

Founded

1998 · Istanbul

Head Office

Çilek Plaza, Eyüp Sultan Mah. Yakacık Cd. Feshane Cd. No: 2 D:4 D:1, 34885 Sancaktepe / İstanbul

Service Area

All of Türkiye · exports to 14 countries

Branches

Kyrgyzstan · Egypt · Algeria · Iraq

Showroom

Plan a showroom visit

At our showroom in Çilek Plaza, Sancaktepe, you can discuss your project with our team. We recommend booking an appointment by phone before your visit.

Working Hours

  • Monday – Friday · 08:00 – 17:30
  • Saturday · 08:00 – 12:30
  • Closed on Sunday
Directions

Frequently Asked Questions

About Swimming pool construction stages, frequently asked questions.

Çilek Havuz Corporate

Pool and Wellness Engineering

Response Time
Same day
Channels
Phone · Email · WhatsApp

If the answer you are looking for is not here, send your question directly to us and our team will reply as soon as possible.

+90 216 475 39 37

A reinforced concrete villa pool has 12 steps. They are site survey, ground investigation, preliminary design, construction drawings, permit, excavation, drainage and blinding, shell concrete, pipework, waterproofing and water-tightness test, finish, and commissioning. Design, permit and site time vary with the ground, the municipality and the pool type; the duration is given in the written project schedule after the site survey.

Çilek Havuz Corporate

The ground investigation, perimeter drainage and the water-tightness test. All three are short and inexpensive steps; skipping them comes back as a shell lifted by groundwater, a buried leak and a finish that has to be removed. In our sequence all three close with a record, and stage payments depend on these records.

Çilek Havuz Corporate

A leak in the waterproofing is invisible under the finish; the finish has to be removed to find it. The test consists of filling the pool and monitoring the level for 48 hours, assessed after deducting the evaporation allowance. The finish does not start until it is passed.

Çilek Havuz Corporate

Look at the output of each step. The outputs are the geotechnical report, construction drawings, excavation level record, concrete samples and pour record, pressure test record, water-tightness test record, finish checklist and commissioning report. Payment is tied to these documents, not to calendar dates.